![]() ![]() Use the Export to Microsoft Project XML option that Oracle Primavera P6 includes.We evaluated a few different approaches to performing the conversion, including: The schedule in question includes about 6,500 activities, with resources not included in the conversion. ![]() do not use the Retain Logic option in the Schedule calculation) then you can get matching or very similar results from Microsoft Project. If you are prepared to abstain from some features of P6 (e.g. There are many differences between Oracle Primavera P6 and Microsoft Project, but there is also a core set of overlaps in scheduling functionality between them. To do this, we have assisted the contractor in setting up a monthly process for conversion and validation of the P6 schedule into the mpp format. On one of their programs, their customer must be provided with a copy of the P6 schedule in Microsoft Project native mpp format each month. We’ve recently been working with an Aerospace contractor who manages their project schedules using Oracle Primavera P6.